We
were contracted by Morgan Ashurst, who are now known as Morgan Sindall, to carry
out works to the new Boots Amenities Block in Nottingham, with an initial
contract period of 10-weeks.
Once on site, we became involved with many other works packages, which resulted
in our contract period being extended and lasting 46-weeks!
Our works involved new blockwork exterior walls to the Restaurant, which were
then covered in a Sto Render System; new partition walls, tiling, floor
screeding, fire boarding, fire stopping and the demolition of Warehouse
partition walls and roller shutters.
Restaurant, which
were then covered in
a Sto Render System;
new partition walls,
tiling, floor
screeding, fire
boarding, fire
stopping and the
demolition of
Warehouse partition
walls and roller
shutters.
We also became
involved with many
of the works in the
“State of the Art”
Distribution
Warehouses. This
included many high
level structural
openings for the new
Conveyor System
through the
Warehouse walls.
Most of these works,
together with the
cladding of the new
support steels, all
took place from
Mobile Elevating
Work Platforms
(MEWPS).
|